10/4 Update

Asalamualaikum everyone!

Here are the recent updates on the masjid construction:

The Sprinkler work has been completed

The Drywall has started

The Minaret roofing is currently being worked on

All exterior doors haven been raised, and final grading is completed alhamdulillah.

9/7 Update:

Asalamualaikum everyone, here are some updates on the masjid construction:

Site work is going on, and the final grading and removal of dirt is complete

The sprinkler system is still pending, and we are waiting for township to issue a permit

The door access, security, and camera system are installed

All the low voltage wiring is completed

Here is a video from back in July linked below:

https://youtu.be/cLEJcPuGrVw

8/9 Update

Asalamualaikum everyone,

alhamdulillah work is going diligently for the masjid construction, here are the recent updates:

  • Framing for the base of the miner at top is installed

  • Sprinkler line is currently being installed

  • Electrical work is being finished

  • Design for the exterior trench drain has been completed

7/19 Update

Asalamualaikum everyone, here are the current updates on the masjid construction:

  • HVAC ductwork is complete

  • Fire sprinkler line connection is complete

  • Interior install is still ongoing

  • Exterior trench drain install still being designed

  • Fire alarm system currently being installed

  • PECO Gas line is complete, and Verizon FIOS Line is almost fully connected

6/22 Update

Asalamualaikum everyone,

here are some recent updated on the masjid construction

• The Elevator is currently being installed

• We are working on finishing up the HVAC installation in the main prayer hall

• Re-design of the of the exterior draining currently undergoing

• All interior gas pipes have been installed.

• Waiting for PECO to install the meter and exterior line

6/1 Update

Asalamualaikum everyone,

Here are the recent updates on the masjid construction:

  • Roof has been succesfully completed

  • We have passed the rough inspection for the plumbing from the township

  • We are currently working on finishing up the electrical and HVAC roughens

  • As we were completed the as-builts the finished floor elevation was found to be less than the design elevation.

  • We are working with the contractor and site engineer to come up with the remedy to ensure the building will be waterproof

4/8 Update

Asalamualaikum everyone!

PECO lines are in alhamdulillah. However, we are still waiting for energizing the bulding.

The plumbing work is on going, and we have added 2 wudu stations to each men and womens bathrooms.

We are currently doing some design changes to the reflected ceiling plan (lighting fixtures and type of ceiling), and site grading is also taking place.

3/9 Update

Asalamualaikum everyone, here are the recent updates on construction:

  • Window installation has been completed

  • Electrical rough-ins are 50% completed

  • The plumbing rough-ins are currently being installed

  • PECO transformer has been installed

  • Stucco install is currently ongoing

  • Rooftop drains have been installed and are currently being connected

2/14 update

Asalamualaikum everyone,

The HVAC has been redesigned alhamdulillah, and we are back on track to getting it installed. The roof work is on going, the exterior insulation is being prepped and placed, and interior rough-ins for electrical have started, plumbing and HVAC to start soon

2/1 Update

Asalamualaikum everyone,

Unfortunately we have experienced a delay; the mechanical design for the HVAC system was not up to par for the masjid.

We needed to revisit multiple items withe the designer and essentially get the HVAC system redesigned.

Alhamdulillah we were still able to keep the same RTU units that we ordered in December. This pushed the project completion about 4 weeks.

But we are still working diligently to keep the project as close to schedule as possible insha’Allah.