Asalamualaikum everyone,
here are the recent updates on the masjid construction!
The exterior patio and sidewalk are completed.
The drywalling and spackling are completed
Painting is underway, and tiling will start soon insha Allah
Community Updates for Egypt Rd construction project.
Asalamualaikum everyone,
here are the recent updates on the masjid construction!
The exterior patio and sidewalk are completed.
The drywalling and spackling are completed
Painting is underway, and tiling will start soon insha Allah
The electrical fixtures and lighting has started
The core plumbing activities in the bathroom are completed
The outdoor speaker and camera dome box has been set up
The indoor staircase work is ongoing
Asalamualaikum everyone,
here are the recent updates on the masjid construction:
The fry wall work is almost finished
The men and women’s entrance doors are installed
The side emergency door is installed
The outdoor concrete flooring is done
Asalamualaikum everyone,
here are the recent updates on the masjid construction:
The minaret roof, hatch and ladder are installed
The meter pit and hot box for the waterline are installed
We have passed the Interior framing inspection
The Elevator hook up is complete!
Asalamualaikum everyone!
Here are the recent updates on the masjid construction:
The Sprinkler work has been completed
The Drywall has started
The Minaret roofing is currently being worked on
All exterior doors haven been raised, and final grading is completed alhamdulillah.
Asalamualaikum everyone, here are some updates on the masjid construction:
Site work is going on, and the final grading and removal of dirt is complete
The sprinkler system is still pending, and we are waiting for township to issue a permit
The door access, security, and camera system are installed
All the low voltage wiring is completed
Here is a video from back in July linked below:
Asalamualaikum everyone,
alhamdulillah work is going diligently for the masjid construction, here are the recent updates:
Framing for the base of the miner at top is installed
Sprinkler line is currently being installed
Electrical work is being finished
Design for the exterior trench drain has been completed
Asalamualaikum everyone, here are the current updates on the masjid construction:
HVAC ductwork is complete
Fire sprinkler line connection is complete
Interior install is still ongoing
Exterior trench drain install still being designed
Fire alarm system currently being installed
PECO Gas line is complete, and Verizon FIOS Line is almost fully connected
Asalamualaikum everyone,
here are some recent updated on the masjid construction
• The Elevator is currently being installed
• We are working on finishing up the HVAC installation in the main prayer hall
• Re-design of the of the exterior draining currently undergoing
• All interior gas pipes have been installed.
• Waiting for PECO to install the meter and exterior line
Asalamualaikum everyone,
Here are the recent updates on the masjid construction:
Roof has been succesfully completed
We have passed the rough inspection for the plumbing from the township
We are currently working on finishing up the electrical and HVAC roughens
As we were completed the as-builts the finished floor elevation was found to be less than the design elevation.
We are working with the contractor and site engineer to come up with the remedy to ensure the building will be waterproof
Asalamualaikum everyone,
the electrical roughing are ongoing, plumbing roughing are complete, and sanitary lines are also complete.
Asalamualaikum everyone!
PECO lines are in alhamdulillah. However, we are still waiting for energizing the bulding.
The plumbing work is on going, and we have added 2 wudu stations to each men and womens bathrooms.
We are currently doing some design changes to the reflected ceiling plan (lighting fixtures and type of ceiling), and site grading is also taking place.
Asalamualaikum everyone,
The exterior stucco work is ongoing. The roof is completed, the plumbing rough-ins are currently being installed; they are about 30% complete. The final shape and color fo the building can now be seen!
Asalamualaikum everyone,
The final stucco layer is being placed, and we are currently looking to get power hooked up to the building on April 8th insha’Allah!
The LVT and tiles have also been delivered on site.
Asalamualaikum everyone, here are the recent updates on construction:
Window installation has been completed
Electrical rough-ins are 50% completed
The plumbing rough-ins are currently being installed
PECO transformer has been installed
Stucco install is currently ongoing
Rooftop drains have been installed and are currently being connected
Asalamualaikum everyone,
The HVAC has been redesigned alhamdulillah, and we are back on track to getting it installed. The roof work is on going, the exterior insulation is being prepped and placed, and interior rough-ins for electrical have started, plumbing and HVAC to start soon
Asalamualaikum everyone,
Unfortunately we have experienced a delay; the mechanical design for the HVAC system was not up to par for the masjid.
We needed to revisit multiple items withe the designer and essentially get the HVAC system redesigned.
Alhamdulillah we were still able to keep the same RTU units that we ordered in December. This pushed the project completion about 4 weeks.
But we are still working diligently to keep the project as close to schedule as possible insha’Allah.
Asalamualaikum everyone,
The exterior insulation is underway, the EIFS (stucco) is 50% done
Utility arrangements for gas, electric, and water have all been finalized.
Interior framing is also completed alhamdulillah.
Asalamualaikum everyone,
some recent constuction updates!
The exterior process has started
The roof top unit brackets and supports are currently being installed
The fire sprinkler has been trenched and the pipe is being installed
The window framing has been completed
Asalamualaikum everyone,
Alhamdulillah The interior framing for the masjid is almost complete, the exterior enclosure is finished, the electrical connection and sprinkler connections are scheduled within the next 2 weeks, and the roof top unit installation will start soon insha’Allah.