Asalamualaikum everyone,
Here are the recent updates on the masjid construction:
Roof has been succesfully completed
We have passed the rough inspection for the plumbing from the township
We are currently working on finishing up the electrical and HVAC roughens
As we were completed the as-builts the finished floor elevation was found to be less than the design elevation.
We are working with the contractor and site engineer to come up with the remedy to ensure the building will be waterproof