9/7 Update:

Asalamualaikum everyone, here are some updates on the masjid construction:

Site work is going on, and the final grading and removal of dirt is complete

The sprinkler system is still pending, and we are waiting for township to issue a permit

The door access, security, and camera system are installed

All the low voltage wiring is completed