2/1 Update

Asalamualaikum everyone,

Unfortunately we have experienced a delay; the mechanical design for the HVAC system was not up to par for the masjid.

We needed to revisit multiple items withe the designer and essentially get the HVAC system redesigned.

Alhamdulillah we were still able to keep the same RTU units that we ordered in December. This pushed the project completion about 4 weeks.

But we are still working diligently to keep the project as close to schedule as possible insha’Allah.